Monday, May 4, 2015

Week 19
----------
Monday           : Budget follow up, DW follow up
Tuesday          : TOS/VMS/STR checking

Monday, April 27, 2015

Week 18
======
Monday       : Follow up budget, ARS tickets, and others
Tuesday      : Follow up budget, ARS ticket and others
Wednesday : EDW program spec, check TOS/STR/VMS
Thursday    : Discussion on PUDO
Friday        : EDW


Monday, April 20, 2015

Week 17
----------
- Project plan to follow up with Eddy
- Exchange rate change on TOS Nim/JRW to test
- Revenue testing by Kartish
- VMS testing
- STR/EOC testing
- EOC requirement verification

20 April - Discussion with JRW/Ratanapon for TOS testing
              Discussion with Eddy for project plan
              Budget follow ups
              TOS exch rate follow up
              STR follow up
21 April - Clear email
              Project planning
              Budget follow up
              Meeting
22 April - Project planning meeting with Chatgamol
              Budget empty CCA cost missing
              Budget TOS BKK issue
              VOPS meeting
23 April - MC today
              Change budget erepo CCA issue
              BKK Stuff/Unstuff issue


Sunday, April 12, 2015

Week 15
-----------
- TOS lumpsum SQL and requrement analysis
- PPV training on 09/04 - 10/04

Week 16
=====
12/4/2015 - ဘ၀မုန္တိုင္းထန္တဲ့ေန႔... အတိုင္းအတာထက္ အရမ္းလြန္ေနျပီ။ သည္းခံႏုိင္တဲ့ အတိုင္းအတာထက္ အမ်ားၾကီးေ်က်ာ္ေနျပီ။ အဆိုးေတြေတာ့ ျဖစ္ေတာ့မယ္...


Tuesday, March 17, 2015

Week 12

Week 12 (16/03 - 20/03)
Monday
      - Surcharge report - Update on revenue owner
      - Clear emails
      - Call from Captain SCI for Variable 1 items
      - Call to SPC for OOG/DG/UC items
      - Email to VOPS vendor to send data files by email
      - Budget (SB) starting deployment upload by LMZ
Tuesday
     - AM med check up
     - PM - meeting/check cost procedures
      - To advise DCS team for voyage mismatch and check in Revenue testing : Done
      - Appraisals
Wednesday
     - IJS by destination Excel to send to SCI
     - Midstream by destination Excel to send to SCI
     - Data Modal changes
     - Equipment Design
Thursday
     - Commission Design and approach
Friday
     - Send progress status to CH/TC/JC
     - Continue above
      - OOG/DG to discuss and draft out screen         : ZT   - Tuesday discussion

Next Week
      - DW TOS package testing                               : ZT/KV
      - DW revenue testing                                      : ZT/Durai
      - PPV user list
      - Rebate
      - Recovery
     

TODO
      - KSM eREPO cost report                                 : DN  -  within this week
      - Surcharge report                                          : KV   - To provide data on Monday
      - VOPS EDI inbound                                        : Durai/KV

Tuesday, February 24, 2015


Week 11 (09/03 - 13/03)
------------------------------
Monday to Thursday : MC
Friday                      : eMail to SCI, general follow up


Week 9 (23/02 - 27/02)
-----------------------------
- Monday : Surcharge report
                 DW schedule discussion
                 VOPS discussion
- Tuesday : Surcharge report
                 DW discussion
- Wednesday : AM - Surcharge report prepare for locations
                             DW schedule discussion
                             VOPS
                             Project summary update
                      PM - Leave
Durai      : eMargin split repo/kastury pc/Project summar update/VOPS
Karthik   : VOPS/Surcharge report location preparation
Htike     : EDI
Sohaila  : BKK Exception/FAC/SAP missing mapping

Sunday, January 18, 2015

WEEK 7 - 09/02/2015 - 13/02/2015
ZT
- Surcharge report
- VOPS sending req spec to vendor
- Margin 1 Req Spec to complete
DURAI
 - Split repo cost                                         - Live
 - PUDO new logic implementation                - Live
 - GBS voyage clean up scheduler                 - ????
HTIKE
- Knowledge sharing of EDI to BKK staff
- EDIs
SOHAILA
- FAC CRs
BERM
- EDI knowledge transfer
PICHAT
- GBS tickets


WEEK 6 - 02/02/2015 - 06/02/2015
ZT
- Surcharge report
- VOPS meeting
- FAC meeting
DURAI
 - Split repo cost                                         - Live
 - PUDO new logic implementation                - Live
 - GBS voyage clean up scheduler                 - ????
HTIKE
- Knowledge sharing of EDI to BKK staff
- EDIs
SOHAILA
- FAC CRs
BERM
- EDI knowledge transfer
PICHAT
- GBS tickets


WEEK 5 - 26/01/2015 - 30/01/2015
ZT
Monday : DW meeting at 3pm
Tuesday : DW spec/Surcharge report

DURAI
 - follow up on EDI generation slowness
 - Split repo cost                                         -
 - PUDO new logic implementation                - Monday give data to user
 - GBS voyage clean up scheduler                 - Tuesday to complete
HTIKE
- Knowledge sharing of EDI to BKK staff
- EDIs
SOHAILA
- Slowness of STVD calculation checking
- Copy 2015 to new version
- Follow up on new version
- Copy 2015 data from dev to prod
- Rollout changes to production
BERM
- EDI knowledge transfer
PICHAT
- GBS tickets


WEEK 4 - 19/01/2015 - 23/01/2015
ZT
- Monday AM : follow up on Sin EDI slowness/ABCD
              PM : Budget STVD procedure fine tuning
- Tuesday AM : Budget STVD procedure fine tuning
               PM : eREPO report scheduling
                      DW meeting
- Wednesday
- Thursday
- Friday
    - Preparation for Monday meeting presentation

DURAI
 - follow up on EDI generation slowness
 - Split repo cost                                         -
 - PUDO new logic implementation                - Monday give data to user
 - GBS voyage clean up scheduler                 - Tuesday to complete
HTIKE
- Knowledge sharing of EDI to BKK staff
- EDIs
SOHAILA
- Slowness of STVD calculation checking
- Copy 2015 to new version
- Follow up on new version
- Copy 2015 data from dev to prod
- Rollout changes to production
BERM
- EDI knowledge transfer
PICHAT
- GBS tickets

Sunday, January 4, 2015

12/01 - 16/01
========

12/01 - MC
13/01 - Explore Power Pivot and share to IT DW team
14/01 - DW Task list and discussion with IT DW team
15/01 - Power Pivot Training inquiry.
           Verification of Sept/Oct figure in DW
           Power Pivot for Surcharge analysis
16/01 - Verification of Sept/Oct figure in DW

Durai : PUDO, breakdown of eRepo for POL/POD
Sohaila : Budget finding out why SP takes long time
Htike    : EDI
Pichet/Berm : GBS support/EDI
======================================

05/01 - 09/01
05/01 - ABCD/Reply for eREpo/DW 50 BL/PowerPivot
06/01 - Full time on DW 50 BL, no other else can do...

** Durai need to complete PUDO
** Why slowness to EDI generation