Monday, April 27, 2015

Week 18
======
Monday       : Follow up budget, ARS tickets, and others
Tuesday      : Follow up budget, ARS ticket and others
Wednesday : EDW program spec, check TOS/STR/VMS
Thursday    : Discussion on PUDO
Friday        : EDW


Monday, April 20, 2015

Week 17
----------
- Project plan to follow up with Eddy
- Exchange rate change on TOS Nim/JRW to test
- Revenue testing by Kartish
- VMS testing
- STR/EOC testing
- EOC requirement verification

20 April - Discussion with JRW/Ratanapon for TOS testing
              Discussion with Eddy for project plan
              Budget follow ups
              TOS exch rate follow up
              STR follow up
21 April - Clear email
              Project planning
              Budget follow up
              Meeting
22 April - Project planning meeting with Chatgamol
              Budget empty CCA cost missing
              Budget TOS BKK issue
              VOPS meeting
23 April - MC today
              Change budget erepo CCA issue
              BKK Stuff/Unstuff issue


Sunday, April 12, 2015

Week 15
-----------
- TOS lumpsum SQL and requrement analysis
- PPV training on 09/04 - 10/04

Week 16
=====
12/4/2015 - ဘ၀မုန္တိုင္းထန္တဲ့ေန႔... အတိုင္းအတာထက္ အရမ္းလြန္ေနျပီ။ သည္းခံႏုိင္တဲ့ အတိုင္းအတာထက္ အမ်ားၾကီးေ်က်ာ္ေနျပီ။ အဆိုးေတြေတာ့ ျဖစ္ေတာ့မယ္...